Large commercial solar energy system

Commercial Greater than 5 MW-AC

What is the Application Process?

DG Systems up to with an AC nameplate rating greater than 5 MW-AC that do not qualify for the NYISO Interconnection Process will follow the processes and procedures in Section III. A. "Applications ≤ 5 MW" of Central Hudson's Interconnection Requirements but may be subject to additional state and federal procedures. Note that timelines and costs may differ from those described in Section III. A. "Applications ≤ 5 MW."

Refer to the Application Process for Energy Storage and Distributed Generation greater than 5 MW guide for more details regarding this process.

 

Central Hudson's Interconnection Guidelines

Interconnection Requirements

BESS Charge and Discharge Schedules

Central Hudson Inverter Settings for greater than 50kW

 

A complete application will include the following documents:

  • NYSSIR Appendix B: Application
  • NYSSIR Appendix H: Property Owner Consent
  • NYSSIR Appendix J: Site Control Certification
  • NYSSIR Appendix K (if applicable): Operating Characteristics, etc.
  • One Line Diagram *
  • Site Plan
  • Inverter Cut Sheet
  • Inverter UL Certification
  • Energy Storage Data Sheet (if applicable)
  • Proposed relay and inverter settings *

* Note that these are subject to Central Hudson review and approval

 

How do I submit a DG Interconnection Application?

Applications are submitted online via PowerClerk, Central Hudson’s Interconnection Online Application Portal (IOAP).

 